Access and Construction Alerts Map
Construction activity may affect road, sidewalk, parking lot, elevator or building entrance access.
For Iowa City construction information, please visit: https://www.icgov.org/government/departments-and-divisions/public-works/engineering/construction-projects
For Coralville construction alerts, please visit: https://www.coralville.org/CivicAlerts.aspx?CID=7
Sign up for alerts
To get email notifications of access and construction alerts, sign up at the link below.
Current Closures
Fire Lane between Field House _Hospital Closure
Replacing existing damaged pavement with new. Pavement will be replaced it in segments to avoid major pedestrian disruptions. This work should take about 10 days weather permitting
Hydraulics Model Annex - Steam service to HLMA
This project replaces steam piping across Court St. south of CRWC. Refer to traffic plan attached.
Medical Education Research Facility - Institutional Roads – Construct New Road – Newton Road to Fountain Entrance
As Part of the Newton to Fountain Road Project, the VA Bus Loop will be Closed Starting on August 10th, 2024. The project continues to progress on schedule and the area of the new road will now also be closed to pedestrian Traffic.
Bus Stops Adjacent to the Dental Science Building and MERF (Eastbound...
UIHC VA Bus Loop Access from Fountain Entry Area - Institutional Roads – Construct New Road – Newton Road to Fountain Entrance
The Institutional Road project is proceeding as scheduled and work will proceed adjacent to Ramp 1 and Boyd Tower. This will interrupt the pedestrian route directly down the hill to the VA bus loop. Access can be achieved by walking around the South side of the Center for Disabilities and...
Repair Hillside at Church and Clinton Street
Sidewalk will be closed for project work associated with restoration of Hillside at the intersection of Clinton and Church Streets. The sidewalk will be opened no later than 8/16/24 for Fall 2024 move in week. Work may need to continue again starting 8/26/2024 which will require additional sidewalk...
Hardin Library for Health Sciences - Institutional Roads – Construct New Road – Newton Road to Fountain Entrance
New road construction from Newton to Fountain Entrance of Hospital will start on May 17th and Continue through Late December of 2024. Temporary re-route of Newton road will be in vicinity of current sidewalk. Detour of sidewalk will be to north side of Newton road. There are additional alternate...
Lot 75 - Engie Water Distribution Storage Relocation Bid Package #1
Site demolition and building of new standpipe and pumping station.
Significant parking space impacts in Lot 75 for the duration of site demolition and construction of the new standpipe and pumping station.
Hawkeye Parking Ramp - Construct Facility
Location: Lot 43, north of West Campus Transportation Center.
Reason for closure is for the construction of a new parking ramp.
Lot 43 has been modified to split the current parking lot into two lots, Lot 43 and Lot 52. The remaining Lot 43 will be out of service while construction of a new parking...
Gerdin Athletic Learning Center - Parking lot closure to Construct Facility
Location: Parking area west of Gerdin Athletic Learning Center
Fencing revisions to accommodate revised HSAB project site following turnover of Lot 14.