Access and Construction Alerts Map
Construction activity may affect road, sidewalk, parking lot, elevator or building entrance access.
For Iowa City construction information, please visit: https://www.icgov.org/government/departments-and-divisions/public-works/engineering/construction-projects
For Coralville construction alerts, please visit: https://www.coralville.org/CivicAlerts.aspx?CID=7
Sign up for alerts
To get email notifications of access and construction alerts, sign up at the link below.
Current Closures
Hospital Parking Ramp 4 - Hospital Parking Ramp No. 4 - Replace Curtain Wall Glazing at Northwest Stairs
The west parking ramp entrance at For the Kids Way will be closed between the hours of 6 pm to 2 am starting on 9/9/2024. Work will be completed on 9/20/2024. The east entrance will be fully accessible to vehicles.
The sideway areas around the elevator and glass areas will be blocked off to allow...
Medical Education Research Facility - Institutional Roads – Construct New Road – Newton Road to Fountain Entrance
As Part of the Newton to Fountain Road Project, the VA Bus Loop will be Closed Starting on August 10th, 2024. The project continues to progress on schedule and the area of the new road will now also be closed to pedestrian Traffic.
Bus Stops Adjacent to the Dental Science Building and MERF (Eastbound...
UIHC VA Bus Loop Access from Fountain Entry Area - Institutional Roads – Construct New Road – Newton Road to Fountain Entrance
The Institutional Road project is proceeding as scheduled and work will proceed adjacent to Ramp 1 and Boyd Tower. This will interrupt the pedestrian route directly down the hill to the VA bus loop. Access can be achieved by walking around the South side of the Center for Disabilities and...
Hardin Library for Health Sciences - Institutional Roads – Construct New Road – Newton Road to Fountain Entrance
New road construction from Newton to Fountain Entrance of Hospital will start on May 17th and Continue through Late December of 2024. Temporary re-route of Newton road will be in vicinity of current sidewalk. Detour of sidewalk will be to north side of Newton road. There are additional alternate...
Slater Hall - Health Science Academic Bldg Utilities Install
Utility installation work for the new HSAB building will involve removal of the sidewalk south of Slater Hall, tying into existing utility systems and restoration of the area. Fencing will be installed to protect the work zone which will block the south entrance (ENT2) to the building. The ADA...
Lot 75 - Engie Water Distribution Storage Relocation Bid Package #1
Site demolition and building of new standpipe and pumping station.
Significant parking space impacts in Lot 75 for the duration of site demolition and construction of the new standpipe and pumping station.
Hawkeye Parking Ramp - Construct Facility
Location: Lot 43, north of West Campus Transportation Center.
Reason for closure is for the construction of a new parking ramp.
Lot 43 has been modified to split the current parking lot into two lots, Lot 43 and Lot 52. The remaining Lot 43 will be out of service while construction of a new parking...
Gerdin Athletic Learning Center - Parking lot closure to Construct Facility
Location: Parking area west of Gerdin Athletic Learning Center
Fencing revisions to accommodate revised HSAB project site following turnover of Lot 14.