Power Plant - Procure and Install Boiler

Project number
0647205
Project building
Project scope
This project will supply and field erect new Boiler #12 inside the Main Power Plant.
Project status
Finance & Operations
Project Budget
$4,551,123.00
Construction start date
Substantial completion date
Awarded to
Locke Equipment Sales Company Incorporated