Project #: |
0248901 |
||
Scope: |
This project recovers site areas on the Art Campus and on the east side of the Iowa River affected by the 2008 flood. |
||
Building: |
General |
||
Project Status: |
Construction Close |
||
Estimated Construction Cost: |
$86,295 |
||
Bid Date: |
9/3/2009 |
||
Bid Results: |
Bid Results | ||
Awarded To: |
Chris Jones Trucking |
||
Construction Start: |
9/8/2009 |
||
Construction Finish: |
10/5/2009 |
||