Project Information
Cambus Maintenance Facility - |
|||
|
|||
Project #: |
0084801 |
||
Scope: |
To construct an 8,000 sq. ft. addition on the south side of the existing Cambus Maintenance facility, at 517 S. Madison Street, to provide indoor storage for a minimum of 12 transit buses. |
||
Building: |
Cambus Maintenance Facility |
||
Project Status: |
Construction |
||
Estimated Construction Cost: |
$1,178,800 |
||
Bid Date: |
10/6/2009 |
||
Bid Results: |
Bid Results | ||
Awarded To: |
Tricon General Construction Inc. |
||
Construction Start: |
11/11/2009 |
||
Construction Finish: |
7/23/2010 |
||
Facilities |
319-335-5500 |
||
|
|
||